New Construction at Woodlawn Village

Share New Construction at Woodlawn Village on Facebook Share New Construction at Woodlawn Village on Twitter Share New Construction at Woodlawn Village on Linkedin Email New Construction at Woodlawn Village link

Overview

In 2011, the Villages at Belvoir garnered national acclaim for the Wounded Warrior Home Project, two concept homes designed by renowned architect Michael Graves to radically redesign the living spaces for the increasing number of Wounded Warriors returning to active duty. Using principles of universal design and lessons learned in the decade since, the construction at Woodlawn Village continues this important mission by delivering eleven new accessible homes and developing an additional 13 accessible home sites.

Plans and specifications comply with the 2015 International Residential Code and 2015 Virginia Building Code (i.e. the applicable codes for new construction in Fairfax County), and were reviewed and approved by the Commonwealth of Virginia, the Fort Belvoir Fire Department, and several third-party consultants approved by the Army. All new homes will undergo rigorous third-party and Army inspections during construction and prior to occupancy.


History of Woodlawn Village

For residents who may not know the history of Woodlawn Village, the neighborhood was developed by the Army around 1980. Following commencement of the Residential Communities Initiative (RCI) in December 2003, Woodlawn Village was targeted for significant upgrades during the project’s Initial Development Period. This included major renovations of the previously built 444 homes, including strategic conversion of 200 existing two-bedroom homes into 100 five-bedroom homes, which provided much-needed housing for larger families assigned to the post. Completed in 2011, Woodlawn Village’s transformation resulted in 336 renovated homes , the two new homes for Wounded Warriors, new playgrounds and amenity areas, and the largest neighborhood center in the Villages at Belvoir, highlighted by an outdoor pool, fitness facility, and indoor and outdoor entertainment space.

Wounded Warrior Homes in Woodlawn Villages

An Inside Look at the Improvements

The plan in 2011, as coordinated with the Army, was to build more single-family accessible homes in open plots of land, also known as “infill lots”, within Woodlawn Village. After several years of engineering, design, and coordination with the Army, the Villages at Belvoir secured approvals for additional accessible homes in Fall 2020.

The eleven new four-bedroom, 2100-SF accessible homes will build upon the elevated standards of design we set in 2011 and will feature brand new stainless steel appliances, quartz countertops, ceramic tiled bathroom floors and showers, water saving fixtures, and energy conserving Nest thermostats, as well as fenced backyards and two-car garages. The initial phase of this development also includes the infrastructure and sitework for all 24 accessible home locations. Similar to how master planned communities are often built off post, finishing lot development now for all accessible home sites will expedite the timeline to build additional accessible homes in the future.






Overview

In 2011, the Villages at Belvoir garnered national acclaim for the Wounded Warrior Home Project, two concept homes designed by renowned architect Michael Graves to radically redesign the living spaces for the increasing number of Wounded Warriors returning to active duty. Using principles of universal design and lessons learned in the decade since, the construction at Woodlawn Village continues this important mission by delivering eleven new accessible homes and developing an additional 13 accessible home sites.

Plans and specifications comply with the 2015 International Residential Code and 2015 Virginia Building Code (i.e. the applicable codes for new construction in Fairfax County), and were reviewed and approved by the Commonwealth of Virginia, the Fort Belvoir Fire Department, and several third-party consultants approved by the Army. All new homes will undergo rigorous third-party and Army inspections during construction and prior to occupancy.


History of Woodlawn Village

For residents who may not know the history of Woodlawn Village, the neighborhood was developed by the Army around 1980. Following commencement of the Residential Communities Initiative (RCI) in December 2003, Woodlawn Village was targeted for significant upgrades during the project’s Initial Development Period. This included major renovations of the previously built 444 homes, including strategic conversion of 200 existing two-bedroom homes into 100 five-bedroom homes, which provided much-needed housing for larger families assigned to the post. Completed in 2011, Woodlawn Village’s transformation resulted in 336 renovated homes , the two new homes for Wounded Warriors, new playgrounds and amenity areas, and the largest neighborhood center in the Villages at Belvoir, highlighted by an outdoor pool, fitness facility, and indoor and outdoor entertainment space.

Wounded Warrior Homes in Woodlawn Villages

An Inside Look at the Improvements

The plan in 2011, as coordinated with the Army, was to build more single-family accessible homes in open plots of land, also known as “infill lots”, within Woodlawn Village. After several years of engineering, design, and coordination with the Army, the Villages at Belvoir secured approvals for additional accessible homes in Fall 2020.

The eleven new four-bedroom, 2100-SF accessible homes will build upon the elevated standards of design we set in 2011 and will feature brand new stainless steel appliances, quartz countertops, ceramic tiled bathroom floors and showers, water saving fixtures, and energy conserving Nest thermostats, as well as fenced backyards and two-car garages. The initial phase of this development also includes the infrastructure and sitework for all 24 accessible home locations. Similar to how master planned communities are often built off post, finishing lot development now for all accessible home sites will expedite the timeline to build additional accessible homes in the future.






  • March 2022 - Construction Updates

    Share March 2022 - Construction Updates on Facebook Share March 2022 - Construction Updates on Twitter Share March 2022 - Construction Updates on Linkedin Email March 2022 - Construction Updates link

    General Notes:

    Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.

    Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    Not entering the site access gates.

    Avoiding the controlled work zones and honoring the construction fence lines.

    Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.

    Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    Siding

    Windows

    Exterior Doors

    Flooring/paint/tile/finishes

    Stormwater management systems in construction and receiving inspections

  • December 2021 - Construction Updates

    Share December 2021 - Construction Updates on Facebook Share December 2021 - Construction Updates on Twitter Share December 2021 - Construction Updates on Linkedin Email December 2021 - Construction Updates link

    General Notes:

    Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.

    Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    Not entering the site access gates.

    Avoiding the controlled work zones and honoring the construction fence lines.

    Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.

    Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    Siding

    Site grading

    Site concrete

    Utilities

    Mechanical/Electrical/Plumbing in-progress.

    Drywall



    Holiday Observance:

    The construction team will not be working on Friday, 12/24 nor Friday, 12/31 in observance of Christmas and New Years.

    Thank you in advance for your patience over the last year as we continue to build new homes for The Villages at Belvoir.



    We would like to wish you and your families a safe and enjoyable holiday season.


  • November 2021 - Construction Updates

    Share November 2021 - Construction Updates on Facebook Share November 2021 - Construction Updates on Twitter Share November 2021 - Construction Updates on Linkedin Email November 2021 - Construction Updates link

    General Notes:

    Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.

    Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    Not entering the site access gates.

    Avoiding the controlled work zones and honoring the construction fence lines.

    Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.

    Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    Framing, roofing, and sheathing will be substantially complete on 11 homes.

    Windows and Siding

    Site grading

    Utilities

    American Water has been working on sanitary and water tie-ins

    Mechanical/Electrical/Plumbing in-progress.

    Drywall

    Site concrete

    Prime painting to be completed on the first two homes.

  • October 2021- Construction Updates

    Share October 2021- Construction Updates on Facebook Share October 2021- Construction Updates on Twitter Share October 2021- Construction Updates on Linkedin Email October 2021- Construction Updates link

    General Notes:

    Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.

    Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    Not entering the site access gates.

    Avoiding the controlled work zones and honoring the construction fence lines.

    Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.

    Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    Sitework continues

    American Water tie-ins progressing

    Mechanical starting

    Electrical starting

    Plumbing starting

    Framing to be completed on 11 homes



  • August/September 2021 - Construction Updates

    Share August/September 2021 - Construction Updates on Facebook Share August/September 2021 - Construction Updates on Twitter Share August/September 2021 - Construction Updates on Linkedin Email August/September 2021 - Construction Updates link

    General Notes:

    Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.

    Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    Not entering the site access gates.

    Avoiding the controlled work zones and honoring the construction fence lines.

    Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.

    Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    Sitework

    Stormwater management

    Wet utilities

    Pouring concrete footings

    Pouring concrete foundations

    Plumbing underground

    Framing in progress

  • July 2021 - Construction Update

    Share July 2021 - Construction Update on Facebook Share July 2021 - Construction Update on Twitter Share July 2021 - Construction Update on Linkedin Email July 2021 - Construction Update link

    General Notes:

    Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.

    Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    Not entering the site access gates.

    Avoiding the controlled work zones and honoring the construction fence lines.

    Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.

    Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    Sitework

    Stormwater management

    Wet utilities

    Pouring concrete footings

    Pouring concrete foundations

    Plumbing underground

  • June 2021 - Construction Update

    Share June 2021 - Construction Update on Facebook Share June 2021 - Construction Update on Twitter Share June 2021 - Construction Update on Linkedin Email June 2021 - Construction Update link

    General Notes:

    Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.

    Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    Inlet Protections

    We’d like to thank residents for their patience and notifications regarding stormwater drainage issues in the neighborhood. As part of the requirements build new homes for service members in Woodlawn, the construction team has installed inlet protections at all stormwater sewer drains.

    These inlet protections are required under the construction permit to prevent illicit discharges of sediment into our storm sewer system and waterways for all construction projects throughout the entire installation. Exceeding the amount of sediment put into the stream systems can have negative environmental impacts as well as result in permit violations, increased regulatory oversight, and stricter requirements in the future.

    While these inlet protections do have some ponding after heavy storms, this is normal and they should draw down within a day or less in most cases. If you have specific concerns about stormwater ponding near inlet protections, please contact the Woodlawn Community Management Office at (703) 781-0566.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    Not entering the site access gates.

    Avoiding the controlled work zones and honoring the construction fence lines.

    Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.

    Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    Sitework

    Stormwater management

    Wet utilities

    Pouring concrete footings

  • May 2021 - Construction Update

    Share May 2021 - Construction Update on Facebook Share May 2021 - Construction Update on Twitter Share May 2021 - Construction Update on Linkedin Email May 2021 - Construction Update link

    General Notes:

    Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.

    Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    We’d like to thank residents for their patience and notifications regarding stormwater drainage issues in the neighborhood. The construction team is working in concert with the Department of Public Works to resolve these issues.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    Not entering the site access gates.

    Avoiding the controlled work zones and honoring the construction fence lines.

    Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.

    Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    Sitework

    Stormwater management

    Wet utilities


  • April 2021 - Construction Update

    Share April 2021 - Construction Update on Facebook Share April 2021 - Construction Update on Twitter Share April 2021 - Construction Update on Linkedin Email April 2021 - Construction Update link

    General Notes:

    • Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.
    • Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.
    • We thank residents for communicating their concerns relating to large tree piles across the neighborhood. Safety fencing, signage, and security services were brought in by the construction team to ensure the security of the stockpiles until removal.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    • Not entering the site access gates.
    • Avoiding the controlled work zones and honoring the construction fence lines.
    • Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.
    • Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    • Sitework
    • Stormwater management
    • Wet utilities


  • March 2021 - Construction Update

    Share March 2021 - Construction Update on Facebook Share March 2021 - Construction Update on Twitter Share March 2021 - Construction Update on Linkedin Email March 2021 - Construction Update link

    General Notes:

    • Project working hours will be from Monday to Friday between 07:00 and 18:00 and Saturday 09:00 to 18:00, except holidays.
    • Neighbors in Woodlawn Village should expect elevated levels of noise as well as increased vehicle traffic during the construction period. There will be an increase of activity outside of the construction fence lines as equipment and materials are delivered.

    Residents can help facilitate this work and ensure quality and safety for everyone by:

    • Not entering the site access gates.
    • Honoring the controlled work zones and do not cross the construction fence lines.
    • Large trucks will be required to perform work, please watch for trucks, equipment, and construction personnel.
    • Ensure that any pets kept in backyards cannot escape and enter the project site throughout the course of construction.

    Work performed during this period will include:

    • Sitework
    • Stormwater management systems
    • Erosion and sediment controls
    • Wet Utilities